Avon Avenue Bridge and Roundabout Project

8-14 Update

Avon Avenue Bridge, Roundabout and Trail Project

Bridge Beams have been installed.

Right Turn lane at US 36 paved.

Roundabout open.


Council approved change order to speed up completion date. It is now November 15, 2017. Contractor will pay liquidated damages if they are not substantially finished by then.  

ROAD CLOSING UPDATE: During construction, Avon Avenue will be open to Frost Bite, Sun Spot and businesses on Galen Drive. We hope you will continue to support these businesses during construction.

                 House on west side of Avon Avenue, just south of Shell gas station, will be used as construction field office.

       Construction bid awarded to Superior Construction for $9,039,054.

      

Project includes a roundabout for 25 South and Avon Avenue and a bridge over the CSX railroad tracks, a trail on the east side and a sidewalk on the west side.

Click here for information on roundabouts: http://safety.fhwa.dot.gov/provencountermeasures/fhwa_sa_12_005.cfm

 

Please check back to this section of our website to view additional details as the project progresses.